Septic
(Septic Installation and placement)
Solar
(Solar Panels,Battery Bank and Inverter Installation)
September 2009
(Ground Breaking - Excavation)
October 2009
(Footings, weeping tile, sump and Level 1 SeaCan Placement)
November_2009
(Heat-sink wall, grounding, strapping, insulation and seacan tower placement)
December 2009
(Securing and Placing More Cans, Main Electrical Panel, Wall openings)
January_2010
(Stairway L1 to L2, Wall and door removal, Exterior Insulation, Backfill)
February_2010
(Painting and Wall Removal, Wood Stove Installed)
March_2010
(Level 2 Chimney, Lighting, Full Wall Removal)
April_2010
(Main House Electrical Panel, Wall Prep)
May_&_June_2010
(Level 1 Main Walls Painting and New Wall Framing and Finishing)
June_2010
(Level 1 Drywall Installation and Finishing)
July_2010
(Passageway and Beam Prep, Painting)
August_2010
(Level 2 Beams Installed, Stair Cases, Seacan Placement and Windows)
September_2010
(Stair Rails, Wall Cut-outs, Window Openings and Heat Tank Pad)
October_2010
(Heat-sink Pad, Dimple Membrane, Beam on Level 3 West, Bracing for Backfill)
November_2010
(Backfill, Level 3 Electrical, ICF Formwork and Boiler)
December_2010
(North Tower Stairwell, Wind Turbine and New Generator)
January_2011
(Level 3 South and North beams, Window Frame Installation and Wind Generator)
February_2011
(Level 3 North beam, New Solar Panel Installation and Level 3 door)
March_2011
(Level 3 Window Framing, Interior Wall Construction and Beam for Level 4 cans)
April_2011
(Beams for Level 4 cans, Level 3 Door Framing and Window Placement)
May_2011
(Balance of Level 4 cans)
June_2011
(Steel for Roof Truss and North Tower Wall Framing)
July_2011
(Mobile Roof Crane, North Tower Roof Opening and Roof Truss System)
August_2011
(Roof Truss System Completion, Top Staircase, Upper Deck Support Mounting and Wall Panel Removal)
September_2011
(Interior Wall Panel Removal, Roof Insulation and Decking, Window and Door Framing, and Exterior Walls)
October_2011
(Roof Decking and Rebar, Exterior Strapping, Insulation and OSB, Backfill Garage Area and Level 4 Electrical)
November_2011
(Concrete on Roof and Garage Door Opening, Exterior Strapping, Insulation and OSB)
December_2011
(Exterior Insulation and OSB)
January_2012
(Exterior Completion, Garage interior perimeter beams and walls)
February_2012
(Garage and Shop Area, Mandoor and Heater)
March_2012
(Snow, Shop Painting, Security System and North Stairwell Electrical)